What are the contents of a standard letter intent?

Project Description

The project title, objective, location and duration

Scope of Work

A brief statement covering project scope, whether civil works or mechanical installations, or engineering services.

Project Cost (with provisional amounts)

Payment Schedule

Stated in percentage (%) or in the respective currencies in lump-sum.

Performance & Liquidated Damages

The amount (in percentage), type of security and the issuance of performance and liquidated damage bonds.

Mobilization Period

Warranty for Work

Usually varies from six (6) months up to one (1) year.

Insurance requirements

Force Majeure

Termination of Contract

Provisions and conditions for either the contractor or the owner to terminate.